Abstract
Ukraine. Territory of construction of the Kakhovska hydroelectric power station. Overpass, dam, shipping lock. Installation of the 1st turbine of the hydroelectric power station in the presence of the engineers of the Kharkov Turbine Works V. M. Osadchev and B. I. Bondarenko. Installers I. V. Korshun, F. T. Kurnev, V. G. Nefedkin, N. G. Osadchuk at work. The head of construction, S. N. Andrianov, the chief engineer of construction, P. S. Neporozhny, are watching the progress of construction from the overpass.
Director
There is no data
Color
B&W
Film ID
17546
Keywords
hydropower
Meterage
124,5
Number of Parts
1
Operators
A. Kovalchuk
Other Creators
There is no data
Release Date
1954
Sound
No Sound